January 27, 2026 - Media Release

Westham Island Bridge Repair Update

Delta, BC – TransLink is moving urgently to restore the Westham Island Bridge following a marine vessel strike on January 20. Engineering inspections have confirmed significant structural damage and, while repairs are complex, work is starting to minimize disruptions and safely reopen the bridge to vehicles as soon as possible.

Detailed inspections show that Pier 5, one of the bridge’s primary support structures, was severely impacted in the collision. This shifted parts of the bridge out of alignment and damaged the bearing that connects the bridge deck to the pier. As a result, Pier 5 is no longer able to safely support vehicle loads.

Due to the age of the bridge, repairs are technically complex and require specialized marine construction. TransLink is advancing engineering and repair design work while coordinating approvals with partner agencies, and securing equipment and materials to reduce delays as construction begins.

Planned repair work includes:

  • Temporarily lifting a section of the bridge to access and repair the damaged area.
  • Replacing damaged piles and beams.
  • Reconnecting the pier to the bridge structure.
  • Completing final safety inspections before vehicles can return.

Repairs are expected to take several weeks. TransLink understands the impact this has on the Westham Island community and is working quickly to complete repairs. Timelines may be affected by factors such as ongoing inspections, soil conditions, tides, weather, and the age of the bridge.

Why a temporary Bailey bridge isn’t feasible
Following a barge strike in 1969, a temporary Bailey bridge was installed at the site within days. TransLink carefully evaluated using that option again, but the circumstances are different. In 1969, the damage was largely limited to the bridge deck, while the underlying supports remained strong enough to carry a temporary span.

In this case, Pier 5 — a critical support — has been compromised. This affects how loads are carried over the structure, and the foundation at that location cannot be assumed to be safe. Because a Bailey bridge still requires sound supports, installing a temporary span would not address the underlying structural issue. TransLink will continue to explore every feasible option, with safety being the top priority.

Free shuttle services now in place

To help residents and visitors move around safely and reliably, TransLink is running two free accessible shuttle services, operating daily from 5 a.m. (on-island) and 6 a.m. (Delta side) to midnight.

On-island shuttle:

  • A free shuttle is now running on Westham Island to improve local access.
  • Temporary bus stops have been installed.
  • Service runs every 30 minutes, seven days a week.

Bridge to Ladner Exchange loop shuttle:

  • A free shuttle operates between the Delta side of the bridge and Ladner Exchange.
  • This shuttle serves all local stops, including Wellington Point Park and Ladner Elementary School.
  • Riders needing additional assistance can call TransLink’s dedicated Westham Island line at 236.883.4758.

Pedestrian access and emergency services

At some point during repairs, a full closure to pedestrians will be required to complete the work safely. During that period:

  • Water taxi service will be available for residents and essential trips.
  • Advance notice will be provided once timing is confirmed.
  • Emergency access will be maintained.

BC Ambulance Service and Delta Fire and Emergency Services have direct access to the island. Metro Vancouver Transit Police also remains on the Delta side of the bridge 24 hours a day.

Looking ahead: replacement bridge planning underway
TransLink is working with funding partners on a 2027 Investment Plan — which is expected to fund construction of a new Westham Island Bridge. Early replacement planning is underway, including engineering design work. TransLink continues to invest in maintaining the existing bridge to ensure safety and reliability.

For the most up-to-date information about the Westham Island Bridge closure, repair progress, and related access options, please visit translink.ca/westham.

Quote:

Kevin Quinn, CEO, TransLink –

“The Westham Island Bridge is more than just a crossing—it’s a vital lifeline for the farmers, families, and local businesses that define this community. I know the recent barge collision and resulting closure has put a massive strain on the community.

We are doing everything we can to restore the bridge as soon as possible, every hour it’s closed is an hour too long. While we are exploring every possible interim option to get traffic moving, our absolute priority is ensuring the span is structurally safe before vehicles start crossing again.

As we move forward, we are staying in lockstep with the City of Delta to support resident’s daily needs and expedite these repairs. I recognize how disruptive this has been for families, farmers, and businesses, and I don’t take that lightly. Thank you for your patience as we do this work safely, carefully, and with urgency.”